|
TSECL has a total capacity
of 110 MW from 3 generating stations viz. Gomuti Hydro-electric Project,
Baramura Gas Thermal Power Station and Rokhia Gas Thermal Power Station.
In addition to this, it has diesel based generating units of 5.85MW,
which are also operational since pre-independence. The unit-wise
capacity of all generating stations is mentioned below.
|
Name of Project |
Unit |
Installed Capacity |
Year of Installation |
Phase |
|
Gumti H.E Project |
Unit-I |
5.00 MW |
1976 |
Phase-I |
|
Unit-II |
5.00 MW |
1976 |
|
Unit-III |
5.00 MW |
1984 |
Phase-II |
|
Baramura Gas Thermal Project |
Unit-I |
5.00 MW |
1986 |
Not
in Operation
and
already
Surveyed off. |
|
Unit-II |
5.00 MW |
1986 |
|
Unit-III |
6.50 MW |
1990 |
|
Unit-IV |
21.00 MW |
2002 |
|
|
Rokhia Gas Thermal Project |
Unit-I |
8.00 MW |
1990 |
Not
in Operation. |
|
Unit-II |
8.00 MW |
1990 |
|
Unit-III |
8.00 MW |
1995 |
Phase-III |
|
Unit-IV |
8.00 MW |
1995 |
|
|
Unit-V |
8.00 MW |
1997 |
Phase-II |
|
Unit-VI |
8.00 MW |
1997 |
|
Unit-VII |
21.00 MW |
2002 |
|
|
Unit-VIII |
21.00 MW |
2006 |
|
|
Total |
142.50 MW |
|
|
|
Less: 3 units of Baramura station |
16.50 MW |
Units I/II/III |
|
Less: 2 units of
Rokhia station |
16.00 MW |
Units I/II |
|
Installed (Hy+Th) Total |
110.00 MW |
|
|
Out of these
stations, first three units of Baramura gas station (French Make) and
first two nos. unit (Phase-I) of Rokhia Project are not working because
of obsolesce. Therefore effective Installed Capacity is
110.00 MW.
Hydel power
There is a small Hydel power
station in south Tripura named Gumti Hydel project having only 3 x 5 MW
capacities.The yearly energy content in the reservoir of Gumti project
is only 60 Million units. Normally 2 units of 5MW each run at a
continuous load of 8 MW and the 3rd one is kept as stand by. It has been
observed during last few years that with this arrangement 100%
generation is achieved, i.e. 60 MU which fulfils the annual target.
Theoretically the PLF is about 53 .33% with one unit as stand by. But
there is hardly any water available at the end of the year and before
next monsoon to increase the generation for achieving higher PLF.
Gas Thermal Project at Rokhia
The project has 6 no. of Gas
Turbine sets of 8 MW each. Unit-VII of 21 MW capacity was commissioned
during August 2002 and is now in operation. Another 21MW capacity
(Unit-VIII) was come into bus on March 2006.
Unit – I has outlived its life. Further,
unit II has been unstable since commissioning. The cost of
reconditioning these units are found to be beyond economical viability.
Therefore survey reports have been proposed for these units.Similar to
Unit IV of Baramura, 50% capacity share of Units V and VI of this
project is to be given to neighbouring states i.e. Manipur and Mizoram.
Appropriate share of energy has to be transferred to these states at net
generation cost.
Unit-VII (21MW) was out of bus from 11th
January 2006 due to major defect developed in the generator. The major
maintenance work has been taken up including replacement of generator
which is likely to be available for generation in the month of June-06.
Unit VIII (21 MW) has been commissioned on
May 31, 2006. Along with rest of the units, the project is generating
40-MW of power from Unit- III, IV, V, VI and VIII. This will reach 50
MW by June-06 after re-commissioning of Unit#VII. Additional generation
would depend on availability of additional gas at the power stations.
The Diesel power house is operated
intermittently, on emergency basis, mainly due to very high cost of fuel
for the same.
Out of 110 MW installed
capacity in the state comprising of Baramura-21 MW, Rokhia-74 MW and
Gumti Hydel project-15 MW the over all generation is 70 MW round the
clock as such the PLF works out at 63.63% for installed effective
capacity the State.
1X21 MW Gas Thermal Project at
Baramura
The first three units have been out lived
their normal life due to prolonged use and further life extension seems
uneconomical because of non-availability of spares from market and huge
funds would be required for this purpose. Preparation for assessment of
book value of the machine & other codal formalities to be observed is
under consideration of TSECL.
A unit of 21 MW was
commissioned on 27th November 2002 and is running at PLF is
almost 95%. The Baramura project has been synchronized with NE Grid in
the ABT regime. Being funded by NEC, this unit is considered as
Inter-state station and hence 50% capacity share has to be given to
neighbouring states of Manipur and Mizoram. With finalisation of power
purchase agreement and issuance of satisfactory payment mechanism
expected to be completed this year, appropriate share of energy is to be
transferred to these states at net generation cost.
Calorific Value of Natural Gas
The rate of Gas consumption
in a gas based Thermal plant depends upon the Heat Rate of the Turbine
as well as Calorific value of the gas. At Rokhia Gas Thermal Power
Station it is observed that Calorific value of Gas varies from month to
month in the range of 8200 to 8300 Kcal/Cum. Union Ministry of Petroleum
fixes the gas price considering Calorific Value of Gas at 10000
Kcal/Cum. Rebate/Premium on the gas price is applicable if the actual
Calorific value of gas differs from the 10000 Kcal/Cum. GAIL indicates
the average calorific value of gas for the particular month in their
monthly gas bills to calculate the quantum of Rebate/Premium applicable.
Ongoing Capacity
Addition in Generation
|
Ø
21 MW
Unit – V at Baramura GT Project. |
Proposed Capacity Addition in Generation
|
Ø
105 MW CCGT
Project at Chakmaghat. |
|
Ø
104 MW
TGBPP at Manarchwak by NEEPCO. |
|
Ø
740 MW
CCGT at Palatana by OTPC. |
|